CONTENTS  
1. Basic Completion Methods  
2. Completion Procedure  
3. Perforating  
4. Stimulation  
2
Well Completion and Stimulation  
GEOPET  
1. BASIC COMPLETION METHODS  
3
Well Completion and Stimulation  
GEOPET  
INTRODUCTION  
Once the design well depth is  
reached, the formation is tested  
and evaluated.  
PLATFORM  
To complete the production well,  
casing is installed and cemented,  
and the drilling rig is dismantled.  
SEA BED  
30’’ CASING  
A service rig is brought in to  
perforate the production casing  
and run production tubing along  
with downhole equipments.  
20’’ CASING  
13 3/8’’ CASING  
7’’ LINER  
Production casing (9 5/8)  
Production begins after surface  
safety equipment installation  
inished.  
ESERVOIR  
4
Well Completion and Stimulation  
GEOPET  
WHAT IS COMPLETION?  
Well completion creates a  
dependable pathway to the surface  
for the hydrocarbons.  
The term ‘completion’ describes  
the assembly of downhole tubulars  
and other safety equipments that is  
required to enable the safe and  
efficient production of oil or gas  
from the well after it has been  
drilled.  
5
Well Completion and Stimulation  
GEOPET  
BASIC WELL COMPLETION TECHNOLOGY  
Each drilled wellbore awaiting completion is unique. Even nearby wells  
drilled to the same reservoir can have differencies in:  
. depths,  
. formation characteristics,  
. and hole sizes  
A wide variety of equipment designs and procedures have been  
developed to provide safe, efficient conduits from subsurface  
reservoirs to the surface in different situations.  
The ideal completion design  
. minimizes initial completion and operating costs,  
. providing for the most profitable operation of an oil or gas well over  
its entire life.  
6
Well Completion and Stimulation  
GEOPET  
TYPE OF COMPLETION  
Natural Completions  
Natural completions are those in which little or no stimulation is required  
for production. Sandstone and carbonate systems with good permeability  
and mechanical stability are ideal for natural completions.  
Stimulated Completions  
These completions are generally applied to improve the natural drainage  
patterns of hard, low-permeability formations. It is used to remove  
barriers that prevent easy passage of fluids into the wellbore.  
Sand-Control Completions  
Sand-control completions support the formation while allowing the flow of fluids.  
They are performed in young, unconsolidated or less mechanically competent  
sandstones.  
7
Well Completion and Stimulation  
GEOPET  
TYPE OF COMPLETION  
The design of a particular completion depends on:  
1. The number and type of productive zones,  
2. The expected pressures and flow rates,  
3. The need to control sand production,  
4. The need for artificial lift or stimulation the regulations  
governing operations in the area.  
8
Well Completion and Stimulation  
GEOPET  
WELL COMPLETION ACTIVITIES  
Well completion activities include:  
Conducting well test  
Setting production casing  
Running production tubing along with  
downhole equipments  
Installing surface safety equipments  
Starting production flow  
9
Well Completion and Stimulation  
GEOPET  
BASIC COMPLETION METHODS  
Once we drill to the target and evaluate our well by  
. Mud analysis: density & viscosity  
. Well logging (electrical, ascoustic, nuclear, etc…)  
. Coring: at bottomhole or sidewall  
. Welltest: bottomhole pressure vs time -> reservoir properties  
Next decision is whether to complete or abandon it????  
In the latter case:  
. set a cement plug or plugs in the hole,  
. possibly recover whatever casing can be removed,  
. and return the drill-site to its original condition.  
The more fortunate is one in which our well not only is productive, but  
economically justifies a completion.  
10  
Well Completion and Stimulation  
GEOPET  
BASIC COMPLETION METHODS  
The next step usually involves the running of the final string of casing - the  
production string.  
The manner in which this is done determines the basic completion  
method and may follow one of several configurations: (interface between  
the wellbore & reservoir)  
. the openhole completion,  
. the liner completion,  
. the cased and perforated completion  
• Without liner  
• With liner  
11  
Well Completion and Stimulation  
GEOPET  
BASIC COMPLETION METHODS  
The openhole completion: the producing formation is not isolated by  
the casing, which extends only to the top of the producing interval.  
The slotted liner completion: which is not cemented and not "tied back"  
to the surface.  
12  
Well Completion and Stimulation  
GEOPET  
BASIC COMPLETION METHODS  
The cased and perforated completion  
. Without liner: cementing the production casing across the  
productive interval and then perforating the casing for production  
. With liner: a liner is cemented and perforated as a cased and  
perforated completion  
13  
Well Completion and Stimulation  
GEOPET  
BASIC COMPLETION METHODS  
One of these configurations will be the basis for the completion design,  
which may incorporate:  
. one or multiple strings of tubing: single, dual, or triple, etc  
. and a variety of tubing components to facilitate production  
(production method): pumping, flowing, etc.  
. from one or multiple zones: single or multiple zones  
For our purposes, a cased and perforated well with a single tubing  
string will serve to illustrate the typical completion procedure.  
14  
Well Completion and Stimulation  
GEOPET  
SUBSEA COMPLETION  
Subsea production systems are wells  
located on the sea floor, as opposed to  
at the surface. The safety equipments  
are installed underwater on the seabed.  
They enable early production from  
deepwater, remote, and marginal fields.  
Subsea production system offer a  
means of producing field extremities not  
reachable by directional drilling from  
existing platforms, or where field  
economics do not justify the installation  
of one or more additional platforms.  
15  
Well Completion and Stimulation  
GEOPET  
2. COMPLETION PROCEDURE  
16  
Well Completion and Stimulation  
GEOPET  
COMPLETION PROCEDURE  
After the contract casing crew runs the final casing,  
cementing follows the usual procedure, although stage  
cementing may be necessary to cement an extremely long  
string.  
The production string has been hauled out to the location  
and the inside diameter checked to make sure that  
imperfections will not prevent the subsequent running in of  
tubing and packers after the string is set.  
17  
Well Completion and Stimulation  
GEOPET  
COMPLETION PROCEDURE  
Special care: to prevent the possibility of future leaks.  
If stage cementing is necessary:  
. the bottom section is first cemented in place and then  
. a series of plugs are pumped down the casing to open ports that  
allow the upper end of the annulus to receive cement.  
After the cement has set, the inside of the casing must be  
. drilled out and  
. flushed clean of cement and other debris to a depth below that of  
the proposed completion.  
It is important that the inside diameter of the production casing be  
clean and smooth.  
18  
Well Completion and Stimulation  
GEOPET  
COMPLETION PROCEDURE  
It is also important that the cement  
form a competent seal between the  
casing and borehole over the entire  
openhole interval. To ensure this,  
an acoustic cement bond log is  
sometimes run on wireline  
to determine if voids exist  
between casing and hole  
because cement has bypassed  
the drilling fluid.  
19  
Well Completion and Stimulation  
GEOPET  
COMPLETION PROCEDURE  
If the bond is poor in an area, particularly if the area is between  
productive formations, a cement squeeze will be required.  
Often the cement bond log is run in conjunction with a gamma ray log  
and a casing collar log. The drilling engineers can correlate this  
gamma ray log with the logs run earlier during formation logging.  
This correlation is important because as we zero in on the target - the  
productive formation - our need to locate tools precisely relative to that  
formation is critical.  
The open hole logging sondes are subjected to a greater amount of  
"drag" when being pulled up the hole, the depths at which formations  
are recorded may differ somewhat from the formation depths on the  
gamma ray log run inside the casing.  
20  
Well Completion and Stimulation  
GEOPET  
Tải về để xem bản đầy đủ
pdf 93 trang yennguyen 16/04/2022 1200
Bạn đang xem 20 trang mẫu của tài liệu "Bài giảng Cơ sở khoan dầu khí - Chương 7: Well completion and stimulation", để tải tài liệu gốc về máy hãy click vào nút Download ở trên

File đính kèm:

  • pdfbai_giang_co_so_khoan_dau_khi_chuong_7_well_completion_and_s.pdf