Some main results of commissioning of the Dalat Nuclear Research Reactor with low enriched fuel

Nuclear Science and Technology, Vol. 4, No. 1 (2014), pp. 36-45  
Some Main Results of Commissioning  
of The Dalat Research Reactor with Low Enriched Fuel  
Nguyen Nhi Dien, Luong Ba Vien, Pham Van Lam, Le Vinh Vinh, Huynh Ton Nghiem,  
Nguyen Kien Cuong, Nguyen Minh Tuan, Nguyen Manh Hung, Pham Quang Huy,  
Tran Quoc Duong, Vo Doan Hai Dang, Trang Cao Su, Tran Tri Vien  
Nuclear Research Institute Vietnam Atomic Energy Institute  
01-Nguyen Tu Luc, Dalat, Vietnam  
(Received 5 March 2014, accepted 13 April 2014)  
Abstract: After completion of design calculation of the Dalat Nuclear Research Reactor (DNRR) for  
conversion from high-enriched uranium fuel (HEU) to low-enriched uranium (LEU) fuel, the  
commissioning programme for DNRR with entire core loaded with LEU fuel was successfully carried  
out from 24 November 2011 to 13 January 2012. The experimental results obtained during the  
implementation of commissioning programme showed a good agreement with design calculations and  
affirmed that the DNRR with LEU core have met all safety and exploiting requirements.  
Keywords: HEU, LEU, physics start up, energy start up, effective worth, Xenon poisoning, Iodine pit.  
I. INTRODUCTION  
hours testing operation without loading at  
nominal power (December, 13rd, 2011).  
Physics and energy start-up of the Dalat  
Nuclear Research Reactor (DNRR) for full  
core conversion to low enriched uranium  
(LEU) fuel were performed from November  
24th, 2011 until January 13th, 2012 according to  
an approved program by Vietnam Atomic  
Energy Institute (VINATOM). The program  
provides specific instructions for manipulating  
fuel assemblies (FAs) loading in the reactor  
core and denotes about procedures for carrying  
out measurements and experiments during  
physics and energy start-up stages to guarantee  
that loaded LEU FAs in the reactor core are in  
accordance with calculated loading diagram  
and implementation necessary measurements  
to ensure for safety operation of DNRR.  
II. PHYSICS START UP  
Physics startup of reactor is the first  
phase of carrying out experiments to confirm  
the accuracy of design calculated results,  
important physical parameters of the reactor  
core to meet safety requirements. Physics  
startup includes fuel loading gradually until to  
approach criticality, loading for working core  
and implementing experiments to measure  
parameters of the core at low power such as  
control rods worth, shutdown margin,  
temperature effect,…  
A. Fuel loading to approach criticality  
The loading of LEU FAs to the reactor  
core was started on November, 24th, 2011  
following a predetermined order in which each  
step loaded one or group LEU FAs to the  
reactor core. After each step, the ratio of  
Main content of the report is a brief  
presentation of performed works and achieved  
results in the physics and energy start up stages  
for DNRR using LEU fuel assemblies, that is  
from starting loading LEU fuel to the reactor  
core (November, 24th, 2011) until finishing 72  
N0  
(N0 is initial number of neutron count rate,  
Ni  
©2014 Vietnam Atomic Energy Society and Vietnam Atomic Energy Institute  
LUONG BA VIEN et al.  
Ni is that to be obtained after step ith) was  
for working core, effective worth of loaded  
fuel assemblies and shutdown margin were  
preliminarily evaluated to ensure shutdown  
margin limit not be violated. Fig. 3 shows the  
current working core of DNRR, including 92  
LEU FAs (80 fresh LEU FAs and 12 partial  
burnt LEU FAs, the burn up about 1.5 to 3.5  
%) and neutron trap at the center. Total mass of  
U-235 that was loaded to the reactor core is  
about 4246.26 g. Shutdown margin (or  
subcriticality when 2 safety rods are fully  
withdrawn) is 2.5 $ (about 2% k/k), smaller  
than calculated value (3.65 $) but still  
completely satisfy the requirement >1% for  
the DNRR. Excess reactivity of the core  
configuration is about 9.5 $, higher than  
calculated value (8.29 $), ensuring operation  
time of the reactor more than 10 years with  
recent exploiting condition. So, it can be said  
that the current working core meets not only  
safety requirements but reactor utilization  
also (ensure about shutdown margin and  
sufficient excess reactivity for reactor  
operation and utilization).  
evaluated to estimate critical mass. At 15h35  
on November, 30th, 2011 the reactor reached  
critical status with core configuration including  
72 LEU FAs and neutron trap in center (see  
Fig. 1 and 2).  
Established critical core configuration  
with 72 LEU FAs having neutron trap is in  
good agreement with design calculated  
results. With 72 LEU FAs, by changing  
position of some fuel assemblies, all new  
criticality conditions were achieved with  
lesser inserting position of regulating rod. It is  
concluded that the above critical configuration  
(Fig. 1) is the minimum one among  
established configurations. The critical mass  
of Uranium is 15964.12 g in which Uranium-  
235 is 3156.04 g.  
B. Fuel loading for the working core  
After completion of fuel loading to  
approach criticality, fuel loading for working  
core was carried out from December, 6th, 2011  
to December, 14th, 2011. During fuel loading  
Fig. 1. Critical core configuration and  
order of loaded fuel assemblies  
Fig. 2. N0/Ni ratio versus number of FAs  
loading to the core  
37  
SOME MAIN RESULTS OF COMMISSIONING OF  
LEU Fuel  
Wet channel  
Dry channel  
Empty cell  
Berrylium  
Aluminum  
Neutron trap  
Fig. 3. Working core configuratiom with 92 LEU FAs  
C. Performed experiments in the working core  
configuration  
working core in configuration with 82 fresh  
LEU FAs and 92 LEU FAs.  
Determination of control rod worth  
Control rods worths and integral  
characteristics in core configuration with 92  
LEU FAs are presented in Table I, Fig. 4  
and 5. Measured results were smaller than  
design calculated results about 12% in  
average.  
To calibrate control rod worth, doubling  
time method was applied for regulating rod  
while reactivity compensation method was  
used for shim rods and safety rods. The  
calibration of control rods of DNRR were  
implemented two time during fuel loading for  
Table I. Effective worth of regulating rod, 4 shim rods and 2 safety rods  
in core configuration with 92 LEU FAs.  
Effective reactivity ($)  
Control Rod  
Measured value Calculated value  
Regulating rod  
Shim rod 1  
Shim rod 2  
Shim rod 3  
Shim rod 4  
Safety rod 1  
Safety rod 2  
0.495  
2.966  
3.219  
2.817  
2.531  
2.487  
2.195  
0.545  
3.237  
3.263  
3.473  
3.086  
2.744  
2.795  
38  
LUONG BA VIEN et al.  
Position (mm)  
Position (mm)  
Fig. 5. Integral characteristics of 4 shim rods  
Fig. 4. Integral characteristics of regulating rod  
Thermal neutron flux distribution  
measurement in the reactor core  
From the measured results, it can be  
seen that the maximum peaking factor of  
1.49 is achieved at outer corner of hexagonal  
tube of the fuel assembly in cell 6-4. Neutron  
distribution of working core has large  
deviation from North (thermal column) to  
South (thermalizing column). Neutron flux  
in southern region of the core (cell 12-1 and  
12-7) is about 28 % smaller than those in  
Northern region (cell 2-1 and 2-7). The  
asymmetry of the reactor core has reason  
from the not identical reflector that was noted  
from the former HEU fuel core.  
Measurement of thermal neutron flux  
distribution following axial and radial in the  
reactor core was carried out by Lu metal foils  
neutron activation. A number of positions in  
the reactor core were chosen to measure  
thermal neutron flux distribution including  
neutron trap, irradiation channels 1-4 and 13-2,  
and 10 FAs at the cells: 1-1, 2-2, 2-3, 2-7, 3-3,  
3-4, 4-5, 6-4, 12-2 and 12-7. Figs 6 to 9 present  
the measured results of axial and radial neutron  
flux distributions of the reactor core.  
1.1  
1.1  
1
1
0.9  
0.8  
0.7  
0.6  
0.5  
0.4  
0.3  
0.2  
0.1  
0
0.9  
FA cell 2-3  
0.8  
FA cell 3-3  
0.7  
FA cell 4-5  
0.6  
0.5  
0.4  
0.3  
0.2  
0.1  
0
0
5
10  
15  
20  
25  
30  
35  
40  
45  
50  
55  
60  
-35  
-30  
-25  
-20  
-15  
-10  
-5  
0
5
10  
15  
20  
25  
30  
35  
Position from the bottom to the top (cm)  
Position from the bottom to the top (cm)  
Fig. 6. Axial thermal neutron flux distribution in  
the fuel assemblies  
Fig. 7. Axial thermal neutron flux distribution in the  
neutron trap  
39  
SOME MAIN RESULTS OF COMMISSIONING OF …  
Fig. 8. Thermal neutron flux distribution of FAs  
and irradiation positions in comparison with  
neutron trap.  
Fig. 9. Thermal neutron flux distribution of the  
FA’s corners in comparison  
with neutron trap  
Determination of effective worth of FAs,  
beryllium rods and void effect  
determined by comparing position change of  
control rods before and after withdrawing FA  
or beryllium rod or before and after inserting  
watertight aluminum tube. Reactivity worth  
values were obtained using integral  
characteristics curves of control rods.  
The measurements of effective worth of  
FAs, beryllium rods and void effect (by  
inserting an empty aluminum tube with  
diameter of 30 mm) were also performed.  
These are important parameters related to  
safety of the reactor. Positions for  
measurement of effective reactivity of FAs,  
Be rods and void effect were chosen to  
examine the distribution, symmetry of the  
core and the interference effects at some  
special positions. Effective reactivity of FAs,  
beryllium rods and void effect were  
Figs 10÷12 show the measured results  
of effective worth of 14 FAs in the reactor  
core at different positions; effective worth of  
beryllium rods around neutron trap and a  
new beryllium rod at irradiation channel 1-4;  
void effect at neutron trap, irradiation  
channel 1-4 and cell 6-3, which surrounded  
by other FAs.  
Fig. 10. Effective worth ofFAs in the reactor core  
Fig. 11. Effective worth of Be rods in the reactor core  
40  
LUONG BA VIEN et al.  
Temperature (0C)  
Fig. 13. Negative reactivity insertion  
dependent on pool water temperature  
temperature  
Fig. 12. Measured results of void effect at  
some positions in the reactor core  
The most effective worth of fuel  
established after each increased step of pool  
water temperature about 2.50C. Basing on the  
change of regulating rod position (due to  
change of temperature in the reactor core) the  
temperature coefficient of moderator was  
determined.  
assembly measured at cell 4-5 is 0.53 $.  
Measured results of effective reactivity of fuel  
assemblies and Be rods show a quite large  
tilting of reactor power from North to South  
direction. Void effect has negative value in the  
reactor core (cell 1-4 and 6-3) while positive in  
the neutron trap. Void effect in neutron trap  
has positive value because almost neutrons  
coming in neutron trap are thermalized, that is  
absorption effect of water in neutron trap is  
dominant compared to moderation effect. The  
replacement of water by air or decreasing of  
water density when increasing steadily of  
temperature introduces a positive reactivity.  
With the core using HEU fuel also has positive  
reactivity of void in neutron trap.  
Heating process of water in reactor pool  
by operating primary cooling pump took long  
time so water in neutron trap also heated up  
and inserted positive reactivity (as explanation  
in measurement of void effect), as opposed to  
temperature effect in the reactor core. So, a  
hollow stainless steel tube 60 mm diameter  
was inserted in neutron trap to eliminate  
positive temperature effect of neutron trap.  
Fig. 13 shows measured results of  
temperature coefficient of moderator with  
Determination of temperature coefficient  
of moderator  
o
initial temperature of 17.7 C. Based on these  
results, the temperature coefficient of  
moderator is determined about -9.110-3 $/oC.  
Measured result without steel pipe containing  
air at neutron trap was about -5.210-3 $/oC.  
Thus, temperature coefficient of moderator  
including neutron trap still has negative value.  
Temperature coefficient of moderator of the  
core loaded with 88 HEU FAs measured in  
1984 was -8.010-3 $/oC.  
Temperature coefficient of moderator is  
the most important parameter, demonstrating  
inherent safety of reactor. To carry out  
experiment, the temperature inside reactor pool  
was raised about 100C by operating primary  
cooling pump without secondary cooling  
pump. To measure temperature coefficient of  
moderator, criticality of the reactor was  
41  
SOME MAIN RESULTS OF COMMISSIONING OF  
III. ENERGY START-UP  
A. Power ascension test  
13-2 and rotary specimen was measured by  
using Au foil activation method. Also, on  
January 17th, 2012 thermal neutron flux of  
positions mentioned above was measured at  
power level 100%. Measured results of thermal  
neutron flux at several irradiation positions in  
the reactor core with different power levels are  
presented in Table II.  
On January 6th, 2012 reactor power has  
been increased at levels of 0.5% nominal  
power, 10% nominal power and 20% nominal  
power. At each power level, thermal neutron  
flux in neutron trap, irradiation channels 1-4,  
Table II. Measured results of thermal neutron flux at several irradiation positions at different reactor power levels  
Power (% Nominal power)  
Irradiation  
positions  
0,5  
10  
20  
100  
Neutron trap  
Channel 1-4  
1.143E+11  
2.063E+12  
4.174E+12  
2.122E+13  
5.288E+10  
4.749E+10  
N/A  
9.719E+11  
8.542E+11  
N/A  
1.965E+12  
1.682E+12  
N/A  
8.967E+12  
N/A  
Channel 13-2  
Rotary Specimen  
4.225E+12  
Based on the reactor power determined  
by thermal neutron flux measurements at low  
power levels, on January 9th, 2012 the reactor  
was ascended power: 0.5%, 20%, 50%, 80%  
and then operated at 80% nominal power  
during 5 hours for determination of thermal  
power and examination of technological  
parameters and gamma dose before raising the  
reactor power to nominal level.  
system parameters was about 372 kW. This  
value enables us to raise the reactor power to  
full power level. 15h32 on January, 9th, 2012 the  
reactor was raised to 100% nominal power and  
maintained at this power about 65 hours before  
decreasing to 0.5% nominal power to measure  
Xenon poisoning transient. Table III presents  
the values of thermal power of the reactor  
during the first 8 hours after the reactor reached  
100% nominal power. The data indicate that  
thermal power is just only about 460 kW, lower  
than design nominal power about 10%.  
Thermal power of the reactor  
corresponding to 80% nominal power level  
(based on indication of control system) after 5  
hours calculated based on primary cooling  
Table III. Thermal power of the reactor with operation time after the reactor reached 100% nominal power  
Tin (1)  
[oC]  
Tout (1)  
[oC]  
GI  
PI  
[kW]  
Time  
[m3/h]  
15h30  
16h00  
17h00  
18h00  
1h00  
29,2  
30,3  
31,0  
31,0  
30,9  
30,8  
30,8  
30,7  
30,6  
30,5  
22,4  
22,9  
23,1  
23,0  
22,9  
22,9  
22,9  
22,8  
22,7  
22,6  
49,4  
49,3  
49,8  
49,8  
49,8  
49,6  
49,8  
50,5  
50,1  
49,6  
390  
423  
456  
462  
462  
454  
456  
457  
459  
455  
20h00  
21h00  
22h00  
23h00  
24h00  
42  
LUONG BA VIEN et al.  
B. Xenon poisoning transient and Iodine hole  
C. Power adjustment  
In the process of gradually raising power  
The experiment to determine the curve  
built up of Xenon poisoning and then  
calculating its equilibrium poisoning was  
conducted from January 9th, 2012 to January  
12th, 2012 when the reactor was in 100%  
nominal power (indicating of control system  
without adjusting power) . Next, Iodine hole  
was also determined from 12 to January 13th,  
2012 after reducing power of the reactor from  
100% to 0.5% nominal power by monitoring  
the shift position of regulating rod.  
in energy start-up, although power indication  
on control system was 100% but calculated  
thermal power of the reactor through flow rate  
of primary cooling system and difference  
between inlet and outlet temperatures of the  
heat exchanger was only 460 kW, smaller than  
nominal power about 10%. The reason was  
mainly due to power density of the core using  
92 LEU FAs were higher than the mixed core  
using 104 FAs before. The adjustment to  
increase thermal power of the reactor was  
performed by changing the coefficients on the  
control panel. After adjusting, the reactor was  
operated to determine thermal power at power  
setting 100%. The results of thermal power  
obtained from the next long operation was  
about 510.5 kW. This value includes 500 kW  
thermal power of the reactor and about 10 kW  
generated by primary cooling pump.  
Fig. 14 presents measured results of  
Xenon poisoning curve and Iodine pit of the  
above  
experiment.  
Xenon  
equilibrium  
poisoning and other effects is totally about -1.1  
eff and the maximum depth of Iodine pit  
determined about -0.15 eff after 3.5 hours  
since the reactor was down to 0.5% nominal  
power. After adjusting thermal power up to  
500 kW, during the long operation from  
March, 12-16, 2012, after the reactor was  
operated 68 hours at nominal power, total  
value of poisoning and temperature effects is  
about -1.32 eff.  
D. Measurement of neutron flux and neutron  
spectrum after power adjustment  
After carrying out reactor power  
adjustment, thermal neutron flux at some  
Xe  
Iodine Pit  
Time (hour)  
Fig. 14. Negative reactivity insertion by Xenon poisoning with operation time and Iodine pit  
43  
SOME MAIN RESULTS OF COMMISSIONING OF …  
irradiation positions in the reactor core and  
start up were carried out successfully. DNRR  
was reached criticality at 15:35 on November,  
30th, 2011 with 72 LEU FAs, consistent with  
calculated results. Then, the working core with  
92 LEU FAs has been operating 72 hours for  
testing at nominal power during from January,  
9th, 2012 to January, 13th, 2012.  
neutron spectrum in neutron trap were  
measured again by neutron activation foils.  
Measured maximum neutron flux at neutron  
trap was 2.23 1013 n/cm2.s (compared with  
calculated result was 2.14÷2.22 1013 n/cm2,  
depending on shim rods position). Those in  
channel 1-4 and 13-2 were 1.07 1013 n/cm2.s  
Experimental results of physical and  
thermal hydraulics parameters of the reactor  
during start up stages and long operation cycles  
at nominal power showed very good agreement  
with calculated results. On the other hand,  
experimental results of parameters related to  
safety such as peaking factor, axial and radial  
neutron flux distribution of reactor core,  
negative temperature coefficient, temperature  
of the reactor tank, temperature at inlet/outlet  
of primary cooling system and secondary  
cooling system,…it could be confirmed that  
current core configuration with 92 LEU FAs  
meets the safety and exploiting requirements.  
and 8.611012 n/cm2.s,  
respectively. The  
experimental error of neutron flux was  
estimated about 7%.  
From reaction rate measured by foils  
irradiation method in neutron trap, neutron  
spectrum obtained by SAND-BP computer  
code. Obtained results of neutron spectrum in  
neutron trap (Fig. 15) showed that comparing  
with mixed-core HEU-LEU fuel, when  
neutron trap having thinner Beryllium layer,  
thermal neutron flux increased while epi-  
thermal and fast neutron flux decreased with a  
significant percentage.  
Measured neutron flux at irradiation  
positions and actual utilization of the  
reactor after full core conversion also  
showed that the reactor core using LEU fuel  
is not much different than previous core  
using HEU fuel.  
IV. CONCLUSIONS  
After completing design calculation and  
preparation, start up of DNRR with entire LEU  
FAs core was implemented following a  
detailed plan. As a result, physics and energy  
Fig. 15. Measured neutron spectrum in neutron trap before and after conversion  
44  
LUONG BA VIEN et al.  
ACKNOWLEDGMENTS  
REFERENCE  
[1] P. V. Lam, N. N. Dien, L. V. Vinh, H. T.  
Nghiem, L. B. Vien, N. K. Cuong, “Neutronics  
and Thermal Hydraulics Calculation for Full  
Core Conversion from HEU to LEU of the  
Dalat Nuclear Research Reactor”, RERTR Int’l  
Meeting, Lisbon, Portugal, 2010.  
The NRI’s staffs that performed start up  
work of DNRR with entire LEU fuel core  
would like to express sincere gratitude to the  
leadership of Ministry of Science and  
Technology, Vietnam Atomic Energy Institute,  
Vietnam Agency for Radiation and Nuclear  
Safety, who have regularly regarded, guided  
and created the best condition for us to  
implement our works. We also express our  
thanks to Argonne National Laboratory and  
experts from RERTR program (Reduced  
Enrichment for Research and Test Reactors)  
and specialists, professionals in program  
RRRFR (Russian Research Reactor Fuel  
Return) has supported in finance as well as  
useful discussions during design calculation of  
full core conversion, upgrading equipments  
and carrying out start up of DNRR.  
[2] L. B. Vien, L. V. Vinh, H. T. Nghiem, N. K.  
Cuong, “Transient Analyses for Full Core  
Conversion from HEU to LEU of the Dalat  
Nuclear Research Reactor”, RERTR Int’l  
Meeting, Lisbon, Portugal, 2010.  
[3] “Process of physics and energy start up for full  
core conversion using LEU fuel of the Dalat  
Nuclear Research Reactor”, Nuclear Research  
Institute, 2011.  
[4] “Operation logbook of DNRR”, 2011-2012  
45  
pdf 10 trang yennguyen 3300
Bạn đang xem tài liệu "Some main results of commissioning of the Dalat Nuclear Research Reactor with low enriched fuel", để tải tài liệu gốc về máy hãy click vào nút Download ở trên

File đính kèm:

  • pdfsome_main_results_of_commissioning_of_the_dalat_nuclear_rese.pdf